Tuesday, October 03, 2006

Ready for the next blocks


The project is temporarily on hold and is ready for the second floor blocks

Tuesday, September 19, 2006

Concrete is poured and went well



The concrete pour is done and the forms are starting to be stripped

Friday, September 15, 2006

Ready for the second floor slab



Having passed inspection, the forming is finalized and the concrete will be poured on Monday. It will take 100 cubic yards to pour the columns, tiebeams and slab along with the stairs.

Wednesday, August 16, 2006

Starting the heavy forming


The scaffolding and materials have been moved from 11th street and are being used to form the tie beams, columns, 2nd floor slab and stairs which will all be poured at one time.

Wednesday, August 09, 2006

Tie beams are being formed


The forming continues for the tie beams, columns, second floor slab and stairs. Material will be brought from the 11th Street location for this forming

Thursday, July 06, 2006

First block walls go up


The blocks are being laid for the first floor today.

Thursday, June 29, 2006

Pouring the slab



The steel has been placed, inspection passed and the concrete is being poured